So far this week, contractors have worked to top coat Surrey Ln, Trailside Way, Tipton Rock Rd, Durfee St, Fairmount Ave & Mass Ave. They have also begun spreading loam, seed and millings as needed at these locations.
On Thursday 9/26/24 contractors will work to complete spreading loam, seed and millings on Durfee St, Fairmount Ave and Mass Ave; completion is weather dependent.
Depending on weather, contractors will return Friday 9/27/24 or Monday 9/30/24 to begin topcoat work on Dennison Dr.
Keep an eye out for future updates.
Please feel free to direct questions to the DPW at 508-764-5403.